There was no work done to the villa between the end of November to the beginning of May as the area of Pointe Milou is protected from construction during the high season.
But we were back to work on May 2nd 2017
By June, the second level of the villa was being raised.
And we kept working on raising the second level.
The roof then came on and now it really started looking like a villa.
By the beginning of August, the entire roof was done.
By the end of the month of August, we had to close down the site as we knew a bad hurricane was coming... the villa had a roof but no windows...